FORT PECK POWERHOUSE TRANSFORMER INSTALL

Projects
  • Fort Peck Powerhouse
    215 Yellowstone Road
    Fort Peck, MT 59223

Scope of work consist of providing the labor, equipment, and materials to remove the existing single-phase GSU Transformer Banks T2 and T4; the existing Oilostatic feeders for Transformer Banks T3 and T4; Movement of two Government Furnished Equipment (GFE) transformers designated KY4A and KZ2A to new permanent locations; provide one new 15 kV feeder for GFE Transformers KY4A; provide new connections for the two GFE transformers; provide new group-operated disconnect 961; provide new protection, control, and annunciation wiring and all the necessary auxiliary systems and ancillary equipment required to install the equipment at the Fort Peck Powerhouse to make the GFE transformers fully operational.

Initial Mobilization / Est Completion Date

3/22/2021 - 11/30/2021

Contract Amount:

7,828,828.00

Job Number:

20-2085

Owner:

USACE - Omaha District
POC: Daniel Monahan

General Contractor:

Koontz Electric Co., Inc.
PM: Stephen Andrews