INDEPENDENCE EHV SUBSTATION PHASE III

Projects
  • Independence Substation
    555 Point Ferry Road
    Newark, AR 72562

Scope of work for phase III auto transformers project included:
*  Replace existing AT1, 400MVA transformer with new 800MVA transformer.  
*  Pull and terminate new cabling
*  Install new bus connections
*  Install new metering 
*  Assist in testing and commissioning.

Initial Mobilization / Estimated Completion Date

11/4/2019 - 6/30/2020

Contract Amount:

$777,390.00

Job Number:

19-2506

Owner:

Entergy of Arkansas
POC: Jonathan Kooiman

Koontz Electric Co., Inc.
PM: Joey Dold
Superintendent: Racy Garis