PINTAIL 345KV SUBSTATION
Projects
-
North side of US 64
Garber, OK 73738
Scope of work consisted of building a new 345kV yard to include, but not limited to 345kV switches, 345kV breakers, all steel support structures, and fabricate all aluminum bus and install. Also included all below and above grade grounding, all above grade conduit, pull and terminate all associated control cable, build out the inside of the control house, build and install the relay panels and all testing and commissioning.
Initial Mobilization / Est Completion Date
5/27/2020 - 9/21/2020
Contract Amount:
$2,382,283
Job Number:
20-2251
Owner:
OG&E
POC: Val Smith
General Contractor:
Koontz Electric Co., Inc.
PM: Joey Dold
Super: Ben Noll