Scope of work consisted of removing EM relays for T1 and T2 protection. Removed 10-5 Aux CT’s for T1 & T2. Removed AD meters from T1, T2 and short CT’s. Installed new transformer 1 and transformer 2 relay terminal protection. Upgraded SCADA and installed telecom rack. This project was completed on time and under budget.
84th STREET SUBSTATION
Oklahoma City, Oklahoma
Initial Mobilization / Completion Date
12/6/2020 - 1/21/2021
Contract Amount:
$113,903.00
Owner:
OG&E
POC Stanley/Wiley
POC Stanley/Wiley
Job Number:
20-2259
General Contractor
Koontz Electric Co., Inc.
PM: Joey Dold
Super: Zach Andrews
PM: Joey Dold
Super: Zach Andrews