BRIDGESTONE 2300V MCC UPGRADE
Russellville, Arkansas

Initial Mobilization / Completion Date

12/18/2019 - 1/4/2020

Contract Amount:

$207,993.00

Owner:

Bridgestone

Job Number:

19-6663

General Contractor

GC: LSI Construction, LLCM
POC: Marcus Sanders

Sub: Koontz Electric Co., Inc.
PM: Stephen Kenney

Worked with Bridgestone to provide the manpower, equipment and material needed to install a new medium voltage MCC along with a new medium voltage Discharge Mill motor.  The project was completed on time and under budget.