Excellence in Construction Award 2020 Project
The scope of work consisted of:
* Removal and Disposal of (19) 480VAC circuit breakers.
* Removal and Disposal of (6) 12SVDC circuit breakers.
* Removal and Disposal of (2) battery disconnect switches.
* Removal and Disposal of conduit and wire connecting battery disconnect switches to the SB Board.
* Removal and Disposal of conduit and wire connecting battery system 1 and 3 to battery disconnect switches.
* Removal and Disposal of underground warehouse feeder & fiber optic cable.
* Removal & Disposal of (6) high voltage motor operators for ground switches.
* Installation of (6) control panels for the motor operated ground switches.
* Installation of DC switchboard in the battery charging room.
* Installation of (33) maintenance switches with blue indication lights, and all associated conduit and wire.
* Installation of (19) digital trip 480VAC circuit breakers.
* Installation of SkV (DP1) switchgear.
* Installation of underground warehouse feeder and fiber optic cable.
* Installation of (6) 12SVDC circuit breakers.