Scope of Work:
Removal and disposal of 3 existing single-phase 115kV and 9 single-phase 230kV transformers.
Install 1 three-phase 115kV and 3 three-phase 230kV transformers, remove existing.
Install new takeoff towers, modify new bus structures, bus work and install oil containment, remove rail track system, demo existing and install new duct bank and power circuits.