Scope of work consisted of the installation of electrical equipment, supports, bus and other components:
· 161kV single phase bus supports (high)
· 161kV single phase bus supports (low)
· 161kV low switch supports
· 161kV high switch support
· H-frame dead end structures
· 13.8kV 50KVA station service with safety switch
· 161kV, 2000A vertical-break switches with associated operating mechanisms
· 161kV, 2000A vertical-break switch with ground switch and associated LLS-II attachment
· 161kV, 2000A vertical-break switch with ground switch and HWS attachment
· 161kV transformer dead end structure
· yard lights
· Porcelain post insulators for bus supports
· 161kV circuit switcher
· Suspension insulator supports on line dead-end structures and transformer dead end structure
· 15kV breakers
· Porcelain insulators on 161kV switches
· 4” schedule 40 aluminum bus with connectors and fitting
· 7 #7 alumoweld shield wire with associated connectors and fittings
· Install 954 ACSR damper cable and jumpers with connectors and fittings
· Install 1272 ACSR jumpers with connectors and fittings
· Install 34.5kV equipment, switches, insulators, bus supports and rigid bus
· Install 34.5kV main breaker, tie breaker, and feeder bay structures
· Install all wire/cable as shown on drawing CB1; includes pulling, stripping, megger testing, and installation of Burndy YAEV lugs
· Install control house relay panels per drawing LO5, including:
· stand along AC panel
· standalone DC panel
· RTU panel
· RTU Peripheral panel
· MOS panel
· transformer differential panel.
· Install 120/240V AC Automatic transfer switch in control house
· Install battery charger and battery DC switch in control house
· Install ADSS for Telecom (estimated 600 ft.)
· Provide and install above ground conduits
· Install distribution backup pad equipment
· Install Transformer Sump Pump and conduit
This project was completed on time and under budget.