INDEPENDENCE EHV SUBSTATION PHASE III
Newark, Arkansas

Initial Mobilization / Completion Date

11/4/2019 - 6/30/2020

Contract Amount:

$777,390.00

Owner:

Entergy of Arkansas
POC: Jonathan Kooiman

Job Number:

19-2506

General Contractor

Koontz Electric Co., Inc.
PM: Joey Dold
Superintendent: Racy Garis

Scope of work for phase III auto transformers project included:

  •  Replace existing AT1, 400MVA transformer with new 800MVA transformer.  
  •  Pull and terminate new cabling
  •  Install new bus connections
  •  Install new metering 
  •  Assist in testing and commissioning.