MOONSHINE ROAD SUBSTATION
Vian, Oklahoma

Initial Mobilization / Completion Date

5/20/2019 - 9/30/2019

Contract Amount:

$699,900.00

Owner:

OG&E
POC: Jim Page

Job Number:

19-2252

General Contractor

Koontz Electric Co., Inc.
Project Manager: Joey Dold
Superintendent: James Russell

Scope of work included:

  •  Build out 161kV bus to include, three 69kV breakers, three new dead end structures.
  •  Install any motor operators and adjust.
  •  Install various potential transformers.
  •  All breaker jumper and control wiring and terminations.
  •  All Control House internals.
  •  Install all substation grid conductors.
  •  Install all control cables.
  •  Megger all outdoor control cables.
  •  Terminate and lip all relaying cables.
  •  Spreading of OG&E supplied gravel to 4 inches coverage over entire substation.
  •  Installing 4 OG&E supplied oil filters inside drain boxes