Scope of work for T-1 modifications consisted of removing the breaker, installing PT, line trap and breaker.
Scope of work for T-2 modifications consisted of furnishing and installing control house cable tray, installation of all substation steel, all electrical equipment and all above grade conduit. Pulled control cable, meggar new cables, installed junction boxes and terminated new cable. Set all panels in the control house, installed and removed temp carpet in control house and built and installed print table. Also included installed all animal mitigation as needed.