The scope of work included replacement of the 13.8kV station service switchgear. Supply and install a voltage regulator, zig-zag transformer and resistor, disconnect switches, bus insulators, panelboards and a dry type transformer. Project required rework of tublar bus to incorporate new equipment. Civil work included excavation and installation of new duct bank, new equipment pads for equipment and containment for the oil filled voltage regulator. Also integration with the plant, testing, commissioning and training. This project was completed on time and under budget.