Greers Ferry Powerhouse  Rehab and Replace MATOC

Greers Ferry Powerhouse
Rehab and Replace MATOC

The scope of work consists of the replacement of Station Service Switchgear and (7) 480VAC motor control centers. The scope of work also consists of the design and replacement of 125VDC and 120VAC Station Control Board, 125VDC batteries, battery chargers, and other...
CAW Jack H Wilson  Water Treatment Plant Phase 2

CAW Jack H Wilson
Water Treatment Plant Phase 2

The scope of work consists of the demolition of existing MV switchgear, power, and controls to 5 pumps and motors. Installation of the new MV switchgear and replacement of the main feeder cable. Installation of the new power, control, and installation for the 5 new...
AR I-30 Crossing River Bridge  Common Duct Bank

AR I-30 Crossing River Bridge
Common Duct Bank

The scope of work consists of the installation of a multi-duct conduit system underhung from the new I-30 River Bridge expansion of the Arkansas River Crossing. Installation of manholes and underground duct at each end to connect to the underhung duct crossing and...
BOBCAT SUBSTATION

BOBCAT SUBSTATION

Greenfield 345KV Switchyard connecting windmill farm generating a total nameplate capacity of 151.8 MW. The scope of work consisted of 345kV switches, 345kV breakers, steel support structures, and fabricated bus work. The main bus line is rated for 11000A and is...
NORFORK POWERHOUSE  MODERNIZATION ELECTRICAL INSTALL

NORFORK POWERHOUSE
MODERNIZATION ELECTRICAL INSTALL

The scope of work consists of the removal of existing generator step-up (GSU) transformers and foundations and the installation of two new Government-furnished GSU transformers and foundations including oil containment modifications. Replacement of 15kV switchgear for...