PRYOR SUBSTATION
Pryor, Oklahoma

Initial Mobilization / Completion Date

10/1/2013 - 7/31/2014

Contract Amount:

$3,174,259.00

Owner:

Confidential Client

Job Number:

13-2003

General Contractor

GC: Whiting Turner
POC: George Fuller

Sub: Koontz Electric Co., Inc
PM: Harold Andrews

Koontz Electric was responsible for the following scope of work:

  1. Site fill and grading.
  2. Sub base and surface rock.
  3. Security fence.
  4. All concrete foundations.
  5. All grounding
  6. Concrete encased duct for 3000 Amp TB4, with (8) 6” SCH 80 PVC. Includes (3) 25KV MV 105, 750 MCM w/ 4/0 GRD per conduit, and (48) 25KV stress cones.
  7. (2) 6” PVC conduits per distribution breaker, and (8) 6” SCH 80 PVC conduits, stubbed outside fence 10 feet.
  8. 1”, 2”, 3” communication conduits. Includes added manhole and pull boxes.
  9. Conduit and cabling for transformer circuits, (CT’s, Alarms, Controls).
  10. Oil Containment System.
  11. All structural steel.
  12. Yard lighting on static masts.
  13. HV bus, fittings, station arrestors, and insulators.
  14. 300 Amp cable bus.
  15. Installation of owner furnished transformer; offloading, placement, assembly, and oil processing.
  16. Installation of switchgear building. Furnish quoted separately.
  17. Crane services for above listed items.