Texas Instruments RFAB2, Above Ground Distribution
300 West Renner Road
Richardson, TX 75080

Initial Mobilization / Completion Date

9/30/2020 - 4/12/2021

Contract Amount:

$1,788,887.00

Owner:

Texas Instruments, Inc.

Job Number:

20-2910

General Contractor

GC: Burns & McDonnell Engineering, Co., Inc.

Sub: Koontz Electric Co., Inc.
PM: James Gammill

Koontz Electric was subcontracted to provide electrical installation for the Above Ground Contractor Scope for the addition at the Texas Instruments RFAB2 Substation. This scope of work included installation of below grade and above grade grounding. Installation of all conduit and ductbanks, including an underground ductbank for two 138kV lines. Installation of new steel, breakers, and overhead bus to 138kV underground ductbank to supply primary power to two transformers. Installation of steel and bus to supply secondary power from the transformers to a new PDC Switchgear Building. And installation of Capacitor Banks and four MV Transformers in the substation. KECI installed and terminated low voltage power and controls, and assisted with final checkout and commissioning of the project.