Jul 24, 2025
SCOPE OF WORK: Rehabilitation of the existing water treatment plant’s facilities, including modifications and upgrades to the Flocculation and Sedimentation Basins, Filters, and other various treatment systems. Construction of a new Bulk Chemical Building,...
Mar 18, 2024
The Memphis Regional Megasite involved constructing and installing essential infrastructure, including developing a Wastewater Treatment Plant, Water Treatment Plant, Water Supply Wells, and Water Towers. The primary goal was to establish a comprehensive electrical...
Nov 16, 2022
Scope of Work: Demolition of existing MV switchgear, power, and controls to 5 pumps and motors. Installation of the new MV switchgear and replacement of the main feeder cable. Installation of the new power, control, and installation for the 5 new pumps and motors....
Aug 20, 2022
Scope of Work: Demolition of existing electrical for the treatment basin, service equipment, and feeders. Install two new MCCs with VFDs, along with additional electrical gear to power new treatment basin and Flash Mix Building. At the new Electrical Building, install...
Aug 20, 2020
Scope of Work: Procurement and installation of the pre-manufactured gatehouse that enclosed new generator, power panels, and control cabinets. Koontz procured and installed the instrumentation devices for water flow and level indication. Koontz also provided power...